Weekly schedule % complete.

Nadeem SyedMember for 18 years 10 months
Created
3
2
0

Hi all,

Just wondering, in P6 if there is any way to get weekly planned schedule % complete in excel.

 

Thanks,

Kind Regards,

Syed

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    planned of what ?what is your

    planned of what ?

    what is your measuring stick 

    assign manhours to each activity then you will know the answer

  2. 0
    Nadeem Syed ·

    Hi, I have manhours

    Hi, I have manhours assigned to each activity, what I'm trying to get in spreadsheet is literally Schedule % Complete, not budgeted units or remaining units or BL budgeted units.

  3. 0
    Zoltan Palffy ·

    your scheduled % complete is

    your scheduled % complete is  from your basline schedule it is the total planned mahours for the project divided by the cumulatived manhours up to that month

    i.e. total planned manhours 100 

    total cumulative manhours at the end of that month = 10 

    therefore 100/10= planned 10% complete

Log in or join to reply