Dear Sirs,

I would like to ask favor/ help for making the Forecast Schedule.

Currently, I already completed the update on our Baseline Schedule to the current cut-off last 24.04.2020.

After I run it , the outcome appears to be a -166 float. With this apprecfiate your help to solve this as my client is already asking.

 

Thank you

 

Regards,

Smoke

4 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi,As I understand from you,

    Hi,

    As I understand from you, you want to get rid of the Negative Float (-166).

    In the Projects Pane:

    1. Select the Project
    2. In the Project Details, Select Dates
    3. Clear the Date shown in the "Must Finish By"

    Or In the Activity Pane:

    1. Trace the Activities with -166 Total Float and Clear the assigned Contraints.

     

    Hope this will help

  2. 0
    Smoke Manibo ·

    Thanks for your

    Thanks for your response.

    Actually I already done that and no negative float appears. One thing is that the forecast dates are now way beyond the original project completiion dates. As I trying to change the dates of some activities some are not moving even I have chnage the relationship or changing the lag.

     

    Thanks

  3. 0
    Zoltan Palffy ·

    1. do as Raymund suggest2

    1. do as Raymund suggest

    2 .filter for any selected filter

    and select both the 3rd and 4th ones in the list 

    has start constraint

    has finish constraint

    these are activities with hard constraint dates if you do not need them remove them

    3. filter for remaining durations over 20 days you could have made a typo in the remaing durations.

  4. 0
    Raymund de Laza ·

    Hi. The issue is due to out

    Hi. The issue is due to out of sequence. Trace the predecessors of predecessors of predecessors of activities that slips beyond project baseline completion date.