How do I build Summary Schedule from details Schedule

Samuel RotimiMember for 8 years 8 months
Created
3
5
0
All, Pls I need help on how to build a summary schedule in P6. How do I identify what should be a summary of the program and how do I build it. Thanks.

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    just think of the major

    just think of the major elements of work and categorize them.

    use the categories to create the wbs structure

    then add you activities to that wbs

     

  2. 0
    Zoltan Palffy ·

    just think of the major

    just think of the major elements of work and categorize them.

    use the categories to create the wbs structure

    then add you activities to that wbs

  3. 0
    Jerome Odeh ·

    Samuel,Once you've identified

    Samuel,

    Once you've identified & categorized the major elements of your schedule as advised by Zoltan, you can set up your schedule as shown in this blog post.

    https://www.plannersplace.com/blog/my-settings-04-schedule-roll-up-in-microsoft-project-p6

    The blog post covers Summary Schedule settings in Microsoft Project & Primavera P6.

    =jerome