Is there any evidence behind the DCMA 5% and 44 working day thresholds?
- Created
- 0
- 21
DCMA 14-point and CIOB PP21 thresholds are often written into specifications as pass marks: 5% missing logic, 0% or 5% hard constraints, 44 working days of float or duration. I've been looking at what evidence sits behind them.
The published work I found:
Griffith (2006), 494 projects: sound CPM practice was associated with finishing closer to plan.
Fitzsimmons et al. (2022), 302 UK infrastructure projects: an Acumen Fuse quality score was not a significant predictor of delay.
Nothing that tests the thresholds themselves, such as whether 5% or 44 days is the right limit.
So I ran a simulation: 22,000 networks with defects injected at known rates, each reported schedule compared against its true network. The main results:
No safe 5% for missing logic or hard constraints. The harm starts with the first defect.
Hard constraints on 1% of activities took 29% of the truly critical activities off the reported critical path, without moving the finish date.
The 5% high-float check failed 99% to 100% of defect-free networks.
Lags made little difference: a quarter of links as fixed lags understated P80 by 4.5%.
Even with every metric combined, around 40% of the variation in delay could not be explained by any static check.
The assumptions are mine. They are set out in the report, with the code and results, so it can be rerun and challenged: ordo.projjex.co.uk/case-studies/programme-quality-study
My question: has anyone seen a study, or kept their own records, that tests whether programmes passing DCMA or PP21 at acceptance actually finish closer to plan?
Declaration: the study is run by my company, Projjex, which makes Ordo, a tool that includes these checks.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
Related across the Open Standard
Knowledge
- Milestone Management
WikiShares "Reporting" · Shares "Schedule development"
- Critical Path
WikiShares "Critical path" · Shares "Schedule development"
- Critical Path DRAG
WikiShares "Critical path" · Shares "Schedule development"
- Logic, Leads & Lags
WikiShares "Logic" · Shares "Schedule development"
- Critical Path Method
WikiShares "Critical path" · Shares "Schedule development"
Discussions
- How many types of activity floats exist in the context of project delivery date(s)?
0 repliesShares "Critical path" · Shares "Logic" · Shares "Schedule development"
- S curve model of adoption rate, Excel
0 repliesShares "Critical path" · Shares "Logic" · Shares "Schedule development"
- Web Based Time Tracking Software
0 repliesShares "Critical path" · Shares "Logic" · Shares "Schedule development"
- No Subject Specified
0 repliesShares "Critical path" · Shares "Logic" · Shares "Schedule development"
- Dredging Productivity
0 repliesShares "Critical path" · Shares "Logic" · Shares "Schedule development"
Blogs
- Blog No 10 - Contractors Progress Reports
Shares "Reporting" · Shares "Delay analysis" · Shares "Schedule development"
- Phantom Schedules
Shares "Reporting" · Shares "Delay analysis" · Shares "Schedule development"
- Programme Planning Standards: The Rules of the Game
Shares "Critical path" · Shares "Reporting" · Shares "Schedule development"
- Culture and Successful Projects
Shares "Reporting" · Shares "Logic"
- Time Equals Money
Shares "Critical path" · Shares "Schedule development"
Jobs
- Planning Claims Analyst
Shares "Reporting" · Shares "Delay analysis" · Shares "Schedule development"
- PMO Analyst
Planning Planet · LondonShares "Reporting" · Shares "Schedule development"
Norms
- Pharmaceutical
Rates, Norms & DurationsShares "Schedule development"
- Elevated Watercourse
Water ManagementShares "Schedule development"
- Health & Healthcare
Rates, Norms & DurationsShares "Schedule development"
- Automotive
Rates, Norms & DurationsShares "Schedule development"
- Rule of Thumb
Rates, Norms & DurationsShares "Schedule development"