Skip to content

Is it better for a GC / DB to revise Orig Dur or just Rem Dur if you find out a procurement is going to take longer?

John ReevesMember for 13 years 5 months
Created
0
4
0

Is it better for a GC / DB to revise Orig Dur or just Rem Dur if you find out a procurement is going to take longer?  (and of course note it narrative - haha) - I have seen only OD and RD required in specs for 35 years when Dur at Completion (or Act) is the most important.  How many times to we have to see OD = 5 RD = 2 DaC = 223 with a giant bar next to it, but no DaC (or Actual Dur) column.   I like DaC more than AD but both get you there.

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?