Hi!

Can anyone explain to me the word "Level" found in Global Change (Selection Tab) and Report Writers (Selection Tab)?

And what does 1-4 means in the Level?

Thanks in advance....

ALFON
SCDC

2 replies

Oldest first
  1. 0
    Mk Tse ·
    ’Level’ means number of layer to each group of selection criteria.
    In Level 1, activities will be filtered out by the list filter. If you have Level 2, the Level 1 result set will further filtered by Level 2 selection criterial, and so onward.
  2. 0
    Lloyd Young ·
    I agree with mktse (China)

    I am always of the opinion that if i dont know then try.

    You have probably produced reports which match this sort of leveling, where you filter for...lets say Hammocks, this is like a level one of the overall plan. Same thing applies in Global change Tab. Basically breaks the plan in to manageable pieces.

    Regards