reports showing periodic datas
In the Open Standard
Emre BayrakMember for 23 years 5 months
- Created
- 3
- 1
0
Hi
I update on weekly basis and update cost related resources monthly, my question is; it is possible to enter ’actual this period’ values, but it is not possible to record these periodic datas, for exp. a activity updated for 3 months , after completion of activity P3 divides the resource values according to durations. but in reality the resource usage can be independent from duration.
So, that problem makes p3 graphic reports useless sometimes.
Up to now ı can not find a way to do it at P3 that is why we solve our problems an excel.
Thanks
Emre BAYRAK
I update on weekly basis and update cost related resources monthly, my question is; it is possible to enter ’actual this period’ values, but it is not possible to record these periodic datas, for exp. a activity updated for 3 months , after completion of activity P3 divides the resource values according to durations. but in reality the resource usage can be independent from duration.
So, that problem makes p3 graphic reports useless sometimes.
Up to now ı can not find a way to do it at P3 that is why we solve our problems an excel.
Thanks
Emre BAYRAK
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?