Skip to content

Baseline showing planned dates

Simon HegartyMember for 22 years 3 months
Created
6
5
0
Hello

im using p3e, when i run a baseline it seems to show the planned dates and not the Start and finish dates, how can I change the settings for this?

thanks

6 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Simon

    I have moved this thread to the P3 forum

    You will get a better response from here.

    Best regards

    Mike Testro
  2. 0
    Dieter Wambach ·
    Simon

    have a look into Admin --> Admin Preferences --> Earned Value --> bottom line.

    Mike

    P3e is just another name for P4/P5/P6.

    Regards
    Dieter
  3. 0
    Mike Testro ·
    Hi Dieter

    Perhaps we need just a primavera forum for P3 to P6.

    I have nevr used any of them to any extent although I have the software.

    Anyway it got your response.

    Best regards

    Mike Testro
  4. 0
    Alexandre Faulx-Briole ·
    Mike,
    could be a good idea: a forum about how to migrate from P3 to P3e/PM (4/5/6), from Primavera to MSP and vice versa
    Alexandre
  5. 0
    Simon Hegarty ·
    Many thanks Dieter
  6. 0
    Dieter Wambach ·
    Mike

    It seems a good idea to establish a new forum.

    Regards
    Dieter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?