Skip to content

Question regarding Transfering Resource - Plz Help

Suresh DevarajanMember for 22 years 3 months
Created
2
3
0
Hi All,
Thank you all for your response to my previous question. Now I am trying to man hour load the schedule. I have concrete budgeted quantity entered in the schedule as a separate resource. I wanted to transfer the resource and it’s budgeted quantity to another schedule.I know I cannot copy all the activities and paste them on the new schedule as the durations vary between the two schedules.
Please let me know how I can transfer the resource id and the budgeted quantity to the respective activities from one P3 Schedule to another.
Thanks,
Suresh

2 replies

Oldest first
  1. 0
    Mk Tse ·
    I submit a reply on this page.

    (Don’t duplicate the post in different forums!)
  2. 0
    Forum Guest ·
    Suresh,

    If the schedule where the resources are to be transferred to have the same activities (ID’s and descriptions) of the schedule you want it transferred from, you can use the export/import facilities of P3 (ver. 3.1 or lower only). It’s a simple two step operation. Be sure to export at least the Act. IDs and all the relevant fields of the resources.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?