Deleting Early Start Constraints

Alfon Lyndon JosonMember for 22 years 6 months
Created
3
4
0
Team...

Can anyone suggest on how to delete Early Start Constrain in Global Change? What is the Command? Thanks in advance and best regards..

ALFON

3 replies

Oldest first
  1. 0
    Paul Maddocks ·
    Not sure it can be done in global change. Quick fix if you have a lot of constraints is to export act ID and constraints data to excel and manually delete the records in excel then import back into P3.
    Make a copy of project 1st, no undo with import/export.
  2. 0
    Luca Basile ·
    For the import/export, find here after the structure of an excel file:
    ACT ECON ECOND LCON LCOND CON COND
    AA1010 XF 16/10/2002
    AA3020 HA
    AA3090 ON 11/08/2004 ON 11/08/2004
    AA3120 EF 30/06/2004
    AA3185 HA
    AA3190 XF 10/05/2004
    AA3280 XF 14/05/2004
    AA4285 HA
    AA5051 ZT
    AA5684 ES 18/08/2003
    AA5686 ES 06/02/2004
    AAAAAA7950 MF 15/10/2004
    AAAAAB2000 MS 07/07/2004
    AAAAAB2001 MS 07/07/2004
    It is not easy to read the first time.
    ECON mean early constrain type
    ECOND used to insert the early date to constrain
    LCON mean late constrain type
    LCOND used to insert the late date to constrain
    CON other date constrain, like expected and mandatory
    COND used to insert the data

    Then
    ES/LS: Ealry/late start
    EF/LF: Early/late finish
    XF: expected finish
    ON: start on
    ZF: zero float
    MF: must finish on
    MS: must start on
    and so on.
  3. 0
    Steven Oliver ·
    A lot easier to just the functions already provided by P3.

    In Glaobal Change, enter in the Then section

    SNE EQ " ", this will remove all early start constraints,

    SNL for late start and so on.

    HTH