Skip to content

Trade Filter

Azvi HanifaMember for 22 years 1 month
Created
6
1
0
Hi Planners

Could any one explain how to Filter planned and actual % of each trade from the master program

Thanks

6 replies

Oldest first
  1. 0
    Raj Maurya ·
    Could you eloborate your question? What exactly you want to do?
  2. 0
    Azvi Hanifa ·
    Hi

    I intent to produce report for each trade progress
    exp:
    Planned% Actual% Slippage
    Earth work ----- ----- ----

    Concrete work ----- ------ ----

    Finishing work ----- ------ ----

    Thanks
  3. 0
    George Stewart ·
    If you set up a new export file, then filter your selection and use the target % complete and actual % complete. run this and you will get the results required.
    See Tools, Project Utilities, Export. If you require more help come back
    George
  4. 0
    Ravi Potwar ·
    Hi,
    Why you want to export the activity.
    You can do from Schedule itself ,Create column Planned % ( Baseline at datadate -Updated % ) Actual% (% completion ) in schedule Itself . Take Print out, If you don’t want Bar chart ,Tick off the Option.
    You can summarised this Schedule as report. I don’t think any problem.

  5. 0
    Philip Jonker ·
    Hi Azvi,

    It is simple, create a resource code for each trade, and add the resources to the program, eg Resource CONC is concrete work, FINI is finishes etc. Then run s-curves for each resource, this will give you what you need.

    Regards
  6. 0
    Azvi Hanifa ·
    Thanks

    Philip

    your answer open the thought, but still if you would elaborate with example and how can open the code from the p3 etc will be more helpful

    Regards

    Azvi

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?