Help! WBS and activity code for Pipeline

Filippo CARTAMember for 21 years 5 months
Created
5
3
0
Hello Guys

I just moved from the aviation industry into a Pipeline Construction company.

The Company I am working for asked me to define a WBS and a list of activity code in order to Plann a new 42 Km Pipeline project using primavera. They never used it before.

Any help

Thanks in advance
Filippo

5 replies

Oldest first
  1. 0
    Philip Jonker ·
    Hi Filippo,

    Interesting they should ask you for a WBS on a pipeline.

    The sequence is easy. Excavate, weld/selected backfill/lay pipe/backfill and compact. I was educated here, and have a lot of experience with Italian contractors WWII POW’s, and they did not know PLANNING OR WBS, BUT THEY ALWAYS GAVE A QUALITY JOB ON TIME.

    It sounds to me that the management heard WBS and don"t understand it. There is beetter ways, of setting up the project by activity coding, rather than WBS, which is to rigid and a pain.

    Bueanna
  2. 0
    Jaco Stadler ·
    For a pipeline type of job (42 km) I would suggest to stay away from Primavera p3 and move to software that uses line of balance. It is so easy and everybody understand it. If you do insist on using p3 then get a software package that can interface with a line of balance package and work from their.

    To do a WBS for a pipeline you must have look at the job Specific. Break the Job down as per the method you are planning to manage the JOB. By Area / Disciple / Phase etc.

    Cheers
  3. 0
    Joy Fernandes ·
    FILLIPO,
    I would advise u to use activity codes over wbs.The sequence would be as follows

    ROW-RIGHT OF WAY
    TRANSPORT/UNLOAD/STRINGING
    TRENCHING/EXCAVATION
    FIELD BENDING/FIELD JOINTING/COATING
    WELDING OPERATION
    NDT
    BEDDING
    LOWERING
    TIE-INNS
    PADDING/BACKFILLING
    REINSTATEMENT
  4. 0
    Dayanidhi Dhandapany ·
    Hi Fillipo,

    The best way is to follow as per the Bill’s suggestion to apply your WBS.

    Cheers

    Daya
  5. 0
    Ulysses Garcia ·
    To satisfies you clients needs . as what Bill says you can use WBS conbined into activity code for as long as you treat it level wise..