Budgeted quantity filter
In the Open Standard
Yves TrudelMember for 21 years 2 months
- Created
- 3
- 1
0
Hi,
I’ve tried to set up a filter based on budgeted quantities, and I coud not find the field in the filter form. I have then created a custum field named BQ1 and made a global change to copy BQ into that new field, and then it worked partially.
My problem is that this custom field gets only the BQ of the last resource in the activity. Say I had 200hrs carpenter and 100 hrs painter in a given activity, P3 will give me only 100 hrs of the painter (considering this is the second resource)
Any solution?
Thanks
PS I work in Primavera 3.1
Yves Trudel
I’ve tried to set up a filter based on budgeted quantities, and I coud not find the field in the filter form. I have then created a custum field named BQ1 and made a global change to copy BQ into that new field, and then it worked partially.
My problem is that this custom field gets only the BQ of the last resource in the activity. Say I had 200hrs carpenter and 100 hrs painter in a given activity, P3 will give me only 100 hrs of the painter (considering this is the second resource)
Any solution?
Thanks
PS I work in Primavera 3.1
Yves Trudel
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?