Regarding Actual Qty in Activity Column

Kannan KGMember for 20 years 11 months
Created
4
2
0
I want to use the Actual qty and qty completed in Activity column. I created actual qty and completed qty as custom data item.

And i added qty as Resources and assign qty in the resources, along with the some other resources also, but when i run gloabl change i am not able to select the single resource budgeted qty, it takes all the resources and the last resources buggeted qty is comming as a result.

how i can select single resources value in gloable change,
or any other method to show the actual and completed qty in Activity column.

Thanks in advance,

Regards,
Kannan

4 replies

Oldest first
  1. 0
    Muhammad Iqbal ·
    use logic in globle change and run

    have fun

  2. 0
    Razi Khan ·
    Hi Kannan,

    Can you elabroate little more with example ?

    Razi Khan
  3. 0
    Jackie Gilliland ·
    Hi Kannan

    I can quickly think of a solution to your problem but this is a pretty roundabout way, but should work.

    create 3 data code fields.
    In the first you will need to manually ad your actual quantity of the resource you would like to measure.

    leave other 2 blank.

    Now create a global change report with.
    If: Leave blank
    Then:Col 2 = Col 1 * pct

    this will give you a value unfortunatly not divided by 100

    Create a 2nd global change
    If: Leave blank
    Then:Col 3 = Col 2 / 100

    This is quite an exercise for what you are looking for, so it depends on how seriously you need to do this. There may be shorter alternatives but this is off the top of my head.

    good luck
    Jackie Gilliland
  4. 0
    Jackie Gilliland ·
    Hi Kannan

    I did a quick check, on my first step below, you could actually load your first column by using a global change rather than to have to load it manually.

    Good luck

    Jackie Gilliland

Log in or join to reply