Dual language

Joel GilbertMember for 23 years 5 months
Created
5
5
0
Dual Language,
If the activity description is filled in English, and I want to have another column next to activity description in Chinese. Is the only way around it to use the Log, one by one?
Is there nothing like MSP a text column? Or is the only way to import from excel but then it alters the Characters?

Anybody with a suggestion?

5 replies

Oldest first
  1. 0
    Jackie Gilliland ·
    Hi Joel

    A possibility is to put it in a custom data field, but you are unfortunately limited to 20 characters.

    Jackie Gilliland
  2. 0
    Hannes de Bruyne ·
    Hello Joel,

    I had this problem a few times with Greek Characters. The best way for me was to import a log Column with the seccond language. But than you have a problem with characters and fonts.
    This problem is caused by the 16-bit problem of P3. Therefore I wrote a small macro in Excel:

    Function TranslateGreek()
    Dim test, zwischen As String
    iRow = 3
    Worksheets("Activity").Activate
    Do While Cells(iRow, 1) <> ""
    Application.StatusBar = iRow - 3
    If Cells(iRow, 19) <> "" Then
    test = ""
    For i = 1 To Len(Cells(iRow, 19))
    zwischen = AscW(Mid(Cells(iRow, 19), i, 1))
    test = test & IIf(zwischen < 256, ChrW(zwischen), ChrW(zwischen - 720))
    Next i
    Cells(iRow, 11) = test
    End If
    iRow = iRow + 1
    Loop
    End Function

    The result of this translation looks funny in Excel,imported in P3 it still looks funny if I use Arial (Like: Âüñåéïò ÊëÜäïò), but as soon as I use a font for Greek as I used it for Windows 95, everthing is . So maybe this works in a similar way for Chinese (Maybe "720" must be changed into another number)

    (I read from Column 19 and write into Column 11)
    Regards Hannes
  3. 0
    Zhang Haixiang ·
    I did this before and no problems.


    First export the activities with a empty log column to DBF.
    Modify the empty log to what you want,
    then import.

    another way to do this is to use P3 batch,It’s not so easy to start. you need take some time to study the P3 batch Manual.

    you may contact www.P3china.com for some language tools,e.g. switch the interface to Chinese....

    hope this helps
  4. 0
    Joel Gilbert ·
    will give it a bash

    Thanks planners
  5. 0
    Serge Marashlian ·
    Again I have the same problem, but this time it is in Arabic. i will try to use the batch option. Thank you fot the help.
    Serge

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?