using actual dates in relationships

Alper TufanMember for 20 years 4 months
Created
3
2
0
my question is about the relationships between activities.i want to link some of the activities with SS+lag not only using the early start dates but also the actual start dates..how can i manage this in p3..
or is it possible to use the actual dates for linking activities?
thanks...

3 replies

Oldest first
  1. 0
    Sukumaran Subaramaniyan ·
    Actual means it is already happen and past. Now the activities are considered as As-Built.

    You can add or reduce the lag to current and future activities only, i.e. after the data date.

    Regards.
  2. 0
    Ronald Winter ·
    Look under Tools / Schedule / Options / General. There you will find the option, "Calculate start-to-start lag from:". Your options are early start & actual start. Good luck!
  3. 0
    Alper Tufan ·
    thank you all..

    regards..