Finish Constraint And Budgeted Quantity

Steve WaackMember for 20 years 2 months
Created
0
1
0
Once your data date is greater than your expected finish date, the duration is zeroed, and the budgeted quantity is zeroed. Is there an autocost rule to leave the bugeted quantity at it’s assigned value and not zero it out?