Skip to content

How to get a S curve for % Planned & % Achieved ?

Sandip ChakrabortyMember for 20 years
Created
5
2
0
Hi,

Pls let me know how we can get a S Curve in P3 for % Planned and % Achieved at any perticular data date.

Can these two curves be superimposed in order to get an idea of the approx lag ( +ve or -ve ) ?

Regards

Sandip

5 replies

Oldest first
  1. 0
    Karim Mounir ·
    Sandip,

    Go to "Tools"-->"Graphic Reports"-->"Resource and Cost".
    click on Add button.
    now number your report and click add.

    1. a window appears click on the tab titled "Resource Selection" and then right click on either "Low Value Resource / Cost Account" (depending on the type of report u want" and select the desired resource/cost account.

    2. on the tab titled "Content" select schedule types that u want to be shown on the s-curve "eg. select current and Target 1 to show actual vs. planned dist." and also select the type of data u want to show "resource or cost".
    on the curve section check the curve type u want to show "histogram bars or scuver or both of them".

    3. on the tab titled "Dates" select the Time Periods which u want to show in your curve and select the interval between dates "eg. days, weeks, months".

    4. I think u can manage the format of the other tabs by yourself "Format, Titles, Pen, Size".

    5. on the tab called "Selection", u can select the report to be shown among certain set of activities or wbs and many other criteria (take a look!).

    6. after finishing all the settings click on run, a window appears, select the desired output method and click on OK and then another window appears confirming to plot the curve click on Yes.

    That’s all, hope it works this time.


  2. 0
    Karim Mounir ·
    Sandip,

    Sorry for forgetting this, u can also refer to the post titled "Plotting the Resources" in the P3 forum.
  3. 0
    Jose Frade ·
    Hello,

    After computing the S curves do not forget to store period performance.
    If not doing it your actual progress curve will change past months values when computing it in future months.

    In order to ensure that computed values do not change it is needed to store period performance.

    BR
    JMFrade
  4. 0
    Alex Wong ·
    Hi Gents

    Layout is also a good platform to display and printout S-Curve

    Cheers

    Alex
  5. 0
    Reynaldo Y. Calayo Jr. ·
    hi guys!

    i agree with jose cause if your not going to have store period performance it will be linear......P3 will distribute it linearly...... and your report will be misleading....

    so from the beginning or start of the project update you have to have store period performance.........

    c",)

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?