PERT functionality ???

Benny LamMember for 20 years 3 months
Created
3
1
0
I used P3 to analyze CPM network, but I want to carry out PERT (Project Evaulation and Reveiw Technique) analysis in P3. I found there is a option (View>>PERT) in menu bar, but it seems just a network diagram mode only.

Could P3 handle PERT network (i.e. input 3 estimated values for each activity duration & perform statistical analysis)???

Thanks for your help.

3 replies

Oldest first
  1. 0
    David Kelly ·
    Benny,

    No, primavera has no probalistic capabilities. The recomended route is to use the "Pertmaster" product which reads and writes data to the primavera project.

    (FYI in "Primavera speak" PERT stands for Primavera’s Easy Relationship Tracking)
  2. 0
    Tahir Naseem PMP, CCE ·
    Dear David
    Thanks for the valuable information and clarify the difference of PERT (Project evaluation & review technique)and Primavera abbreviation
    Tahir
  3. 0
    Benny Lam ·
    Dear David,

    Thank you so much for your help!