Skip to content

Marked boxes on PERT View

Nicolas BergerMember for 20 years 4 months
Created
6
1
0
Hi !

I was wondering to what corresponds Marked boxes on PERT view ?
I mean some activities are normal and some are striped ?
What’s that ?

Thanks by advance.

6 replies

Oldest first
  1. 0
    Ashraf Jahangeer ·
    Nicolas,

    By striped if you mean X crossed , then it is the completed activites.

    Regards,

    Ashraf
  2. 0
    Nicolas Berger ·
    No, only one diagonal through the box, plus I only have activities not started....
  3. 0
    Ashraf Jahangeer ·
    Check Again,

    Single diagonal line is for started activites. You must have put Actual start date for these.

    Regards,


    Ashraf
  4. 0
    Nicolas Berger ·
    Actually, there is no start date but there is % complete greater than "0".

    Thanks anyway...
  5. 0
    Ashraf Jahangeer ·
    How can there be % complete without start, anyway I hope you have now fixed the problem.

    Regards,

    Ashraf
  6. 0
    Nicolas Berger ·
    I know it’s strange but this is the way I received the schedule...
    Anyhow, those activities have constraints...

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?