Guys,

Using global Change, how can i store the cummulative budgeted manhours of different resources in another seperate resource or in CDI ?





1 reply

Oldest first
  1. 0
    Jose Frade ·
    Hello,

    Creating a variable in memory and adding all resources you wnat to that variable.

    (If scrolling some examples provided for other cases with Primavera you will find the steps).

    When total value is reached store it to resource you want and reset momery variable to zero.

    I hope it helps.