How do i force p3 to extend my duration for a certain month (ramadan)-working hours is shorter.



regards,

kier

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Kier,
    assuming that your project’s planning unit is Day:
    a) create a new calendar in which you will have one working day less than the regular calendar (i.e. Sat - Tue instead of Sat - Wen if your regular week is 5 days from Saturday)
    b) assign this new calendar to activities that will occur during the month of ramadhan
    I have used this procedure to schedule projects in Algeria, result is that an 5 day activity will span from saturday morning to next saturday evening
    All the best,
    Alexandre