Updating Targets

Jonathan WardMember for 19 years 8 months
Created
3
1
0
morning Ladies/Gents,
dont know if this is possible,, i have a target(Baseline) Schedule that i would like to up-date, by this i mean, i have added one or two new activities to my ’current’ schedule that are not on the Target, i understand how to up-date the entire Target but i would just like to add the two new activities to the Target without effecting the other activities already present,,, can this be done?
many thanks
Jon

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi Jon,

    Yes it can be done. Open your target project and add new activities and close. When you open your actual project assumming that it is also updated, the new added activities on target should be shown on your schedule together with your actual project.
  2. 0
    Jonathan Ward ·
    thats great, thanks Rodel
  3. 0
    Muhammad Dawood ·
    hi Jnathan:
    i think u can update the schedule after adding the new activities and rescheduling the new target then update

    if u using p3e u have to copy the old target and adding new activities the rescheduling again

    if u using p5 u adding the new activities and making new basline then comparing btween new and old baslines then update the schedule