Calculating duration for summary tasks

Ijaz AhmadMember for 20 years 3 months
Created
1
1
0
Hi guys!
I am finding trouble to customize the duration setting for summary tasks in P5. What I am seeing is that P5 calculates the duration of summary tasks based on calender 5days x 8 hrs/day. How can I change this setting?

1 reply

Oldest first
  1. 0
    Bijaya Bajracharya ·
    Ask this question in Primavera Enterprise - Teamplay / P3e & P3ec forum.

Log in or join to reply