How to link schedules?

Ghassan ZihriMember for 20 years 5 months
Created
4
4
0
Hello planners,

I am using P3.1 and looking to reduce the number of activities in my schedule. Therefore is there is a way to link one schedule to another with one hammock activity only? What are your suggestions/solutions in this regard?

Regards,

4 replies

Oldest first
  1. 0
    Brennan Westworth ·
    If they are sub-projects of the same project group this isnt a problem.

    I have never tried to use interproj for hammocks, but i imagine it wouldnt work.
  2. 0
    Karen Smith ·
    Hi Ghassan,
    Do you mean reduce the number of activities by linking to your other schedules and thus reducing repetition?
    If so can your other schedules be sub-projects and then link with milestones, I haven’t used/considered a hammock but the milestones work well.
    Cheers.
    Karen
  3. 0
    Ghassan Zihri ·
    Hi,

    thank you for your reply. I want to create a hammock activity in one program then to link this activity to an external program. My purpose is to reduce the number of activities of the program that I submit to the Engineer Representative. "Interproject" offers the option to link 2 programs with a FS link. I will keep trying and let you know.

    Regards,
  4. 0
    Gün Göksu ·
    hello,

    "Interproject Relationships" is what you are looking for.

    password: INTRPROJ

    it is located under:

    P3PROGS\INTRPROJ.EXE

    please read the related help files BEFORE doing any changes.
    Always write the changes down, link between milestones clearly defined as "linked/from". If you don’t do this, after some time, you will forget they are there and wonder (possibly spending hours in the process) why the schedule is acting weird.

    hope this helps.

    Gün :)