Is there a way to undo Store Period Performance?

Ashish AbrahamMember for 19 years 10 months
Created
1
1
0
Hello,

I was wondering if there was a way to undo Store Period Performance in P3. I ask, since I need to recover figures of manpower usage from a P3 schedule, in which those figures have been "removed" since Store Period Performance was applied earlier.

Thanks.

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    No, you can’t; if I remember well, you get a warning saying so when you click to store period performance
    the only way to "remove" it is to backup your project schedule before doing it, and restore the schedule when you need it
    Alexandre