Hi all,

Can i ask a question regarding to formating of relationships (links).

In PERT view, we can chage the format of relationship by go to Format/ Relationship to change the color or line style. However, in Bar view, i could not find that function so far.

Can you advise whether that function is availablein Bar chart view or not?

Thank you so much

2 replies

Oldest first
  1. 0
    Arnold Puy ·

    Unfortunately not.
  2. 0
    Tommy Nug ·
    Thank you, Arnold,

    Our project used Sure-track to prepare the programme, and Line styles in Sure-track and P3 are different. Since my manager can not see the links clearly my printings – especially in non-driven tasks, I want to change the line style. If it can not be changed, I must use Sure-track back