histogram for actual and planned manpower in P3

Umer MehmoodMember for 18 years 4 months
Created
4
3
0
Dear All

I am unable to draw histogram that shows both actual and planned man power per week or per day (any time) todate .

thankyou for reading my question

Regards

Umer Mehmood
Planning Engineer

4 replies

Oldest first
  1. 0
    Mohammed Mujtaba ·
    Dear Umer,

    You can get the planned manpower from resource loading. The actual manpower can be tracked daily based on site reports.
  2. 0
    Umer Mehmood ·
    Thank for Reply

    Actually i want the report on primavera outlook format,i can generate report in excel but it looks fabricated ,Primavera reports give look a system generated report and people believe that it has not been fabricated (although it can be fabricated even in oulook form)

    thanks for replying
  3. 0
    Ahmed Khan ·
    Umar,

    Did U get the solution for the above question..?

    If yes plz forward me to onlyazeem4u@yahoo.co.in

    Regards

    Maask
  4. 0
    Umer Mehmood ·
    I did not get the answer from any one
    but
    i thought of one answer

    Primavera can give values of current project planned progress and other on target one ,if we make target plan in such a way that the oll ather things remain same expect planned resources than we can enter actual value in the target plan ,
    Be carful in updating the target and donot update resources , this method can give
    planned histogram
    actual target histogram

    Hope you have pick it

    Regards

    Umer