How to Move Date Sight Line?

Sam AbbittMember for 17 years 9 months
Created
4
2
0
We have a contract schedule that was issued in December. The dates cannot be altered. However, I want to print a copy of the December schedule, but with the Date Sight Line indicating today’s date. I can’t figure out how to move the line to today’s date without running the schedule and changing the early start/finish dates. Can someone please tell me how to do this? I am using Primavera P3. Thanks.

4 replies

Oldest first
  1. 0
    Jean-Philippe Sampieri ·
    Hi Sam,

    If it is only for printing, a turnaround for your problem may be:
    (Make backups before !)
    - Make a copy of your schedule,
    - Set the copy as a target for your schedule.
    - Update the data date of the current schedule
    - In the bar chart, hide all the bars but the Target Bar.

    Hope this helps
  2. 0
    Sam Abbitt ·
    Not sure why, but when I go to copy the schedule it keeps telling me "Invalid Project Name".

    Any ideas?
  3. 0
    Sajid Balma ·
    1. Click Data
    2. Click Calendars...
    3. Click Global Calendar
    4. Click Standard...
    5. Select a new date under Data Date
    Close windows
    Now your schedule has new sight line as per your new data date without any change in the schedule.

    TAAAADAAAA
  4. 0
    Sam Abbitt ·
    Thanks everyone.