Hai to all,

After updating the program, I want to filter those activities which have
1.Actual start less than data date
2.Percentage = 100
3.No actual finish date

Example:

Name E.Start E.Finish Percentage
A 01-Apr-10(A) 01-May-10 100%


I used the following filter

Criteria - All
Early finish GT DD+OD
Percentage EQ 100

but it is not working

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Vijay,
    Try this:
    Criteria - All
    Actual Finish EQ (blank)
    Percent Complete EQ 100

    Another way is if specific:
    Criteria - All
    Actual Start LT DD+1d
    Percent Complete EQ 100
    Actual Finish EQ (blank)
  2. 0
    Vijay N.K. ·
    Thanks Mr. Rodel,


    I got it. This is the first time i am hearing that, leave the box blank. Thanks alot.


    Regards
    Vijay
  3. 0
    Shah. HB ·
    Hi Vijay

    You can use multi levels if you find difficulty in using filter conditions