P3 changing dates

Mike MillerMember for 16 years 5 months
Created
2
1
0
See the pictures for reference.

before

after

Why is it changing the construction activities so they strart at the beggining when they are supposed to be succesors of "Construction"

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Mike,
    The problem is the predecessor because it was progress 100 percent complete sitting after the data date therfore the successor will run on the data date.

    Note: All actual progress activities specially completed should sit after the data date and remaining will run after the data date.
    Data Date mean Status date (cut-off of actual completed activities).
  2. 0
    Shah. HB ·
    Hi Mike

    The way you run the schedule is quite incorrect

    You use actual dates to the activities but the data date is not scheduled accordingly

    Data date is the start date to run the scheduling algorithm

Log in or join to reply