Hello PP members,

Do any one have any experience using Project Issues on P3e e/c??

Regards,

Marcio Eduardo
Rio de Janeiro - Brazil

3 replies

Oldest first
  1. 0
    Marcio Sampaio ·
    I would appreciate to know a practical example.

    Regards.
  2. 0
    David Forrest ·
    I have always used the "issues" in Primavera Enterprise. I use it mainly to monitor and track problems (not risks)
    Normally I include 3 sections in the notes field

    Issue

    Impact

    Proposed Solution

    These field can be emulated in myPrimavera to give some pretty smart reports.

    It depends on what you expect from the feature !!!!
  3. 0
    Marcio Sampaio ·
    Thanks David.