Skip to content

Average Float figure for the project

Kevin MatthewsMember for 20 years 4 months
Created
5
23
0
G’day,

We need the average activity float for the project as we can then track this figure on a weekly basis and show slippage etc..

I have had a quick look for any report that gives me this figure but couldn’t see anything.

I am probably going to export the activities and float for each activity to an excel spreadsheet and then work it out from there (I’m assuming I can do this?)

Is there a quicker and easeir way using P5 ?

Keep Planning (and Happy Christmas)

Kevin.

5 replies

Oldest first
  1. 0
    Johny Kesserwany ·
    what do you mean by ’average activity float’?

    JK
  2. 0
    Wai Chan ·
    I am a new member and just trying to help, maybe this is not the right answer. But I would suggest doing a filter with a range of the float that you want. you probably have to figure out the average float yourself.
  3. 0
    Kevin Matthews ·
    All,

    Average float to me means adding up the total float for all activties and then dividing by the no. of activities. This is then calculated on a weekly basis and inthe weekly project report this number is used as one of many indicators on the project progress. As the average float number decreases this would show the project is becoming more critical (the norm!) ; if the average float figure increases (never seen this!) this will show that progress is good and probably ahead of schedule.

    Keep Planning,

    Kevin.
  4. 0
    David Kelly ·
    Once upon a time, back in the days of manual forward/backward pass when ships were built on the River Clyde, the "Float Trend" chart was a big document.

    We kept track of the change of float each week on some activities. All activities would have been nice, but computers were precious commodities in those days and not freely avaialble for imagineering.

    If you copied the Total and or Free float to a user defined field after each progress run you have a value for float that rolls up, an indication of each activity’s change AND "Group and Sort" would also give you interesting sub-totals
  5. 0
    Kevin Matthews ·
    Thanks David, I’ll try your method.

    Keep Planning,

    Kevin.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?