How to Export Actual % Complete Vs. Planned % in Excel

Cecil SolivaMember for 22 years 7 months
Created
3
23
0
Good Day Planners,

Any planners could help me exporting Actual % Complete Vs Planned % in Spread sheet (Excel)showing time period, say by weekly or monthly? or is this possible in P6?

Thank you,

Cecil

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Cecil,

    You can use "Reports" Directory or "Assignment". But you need to convert this data into percent in Excel by dividing them into 100.

    Go to Project --> Resource Assignments.

    Regards,

    Arnold
  2. 0
    Cecil Soliva ·

    Thanks Arnold...


    cecil
  3. 0
    Arnold Puy ·
    Hi Cecil,

    You are Welcome.