Display Selective WBS

Asyraf MrMember for 17 years 2 months
Created
2
21
0
Hello guys,

How to display and print selective WBS in ’Activities’ window?

Regards,
asyrafr

2 replies

Oldest first
  1. 0
    Mk Tse ·
    Consider group activities by WBS, then double click on WBS headings to collapse all activities
  2. 0
    Alaa Al haj ·
    Hi
    Group Activities By WBS
    and then make filter for a specific WBS toy want to print
    filter will be
    WBS isunder ( the value you want)

    Yours
    Alaa