Fail to import mpp file

Izam ZakariaMember for 20 years 5 months
Created
4
17
0
Guys,

I did so many times to import MPP file but software feedback as follows:-

Import/Export Error: Cannot find a unique value for proj_short_name in PROJECT.

What should I do? please lend me your hand

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Izam,
    What version of MPP are you importing? P6 supports only MSP 2003 and below.
  2. 0
    Daniel Limson ·
    Izam,

    You need to save your MSP file to mpp file with an mmp file extension. When importing to P6, make sure you are importing the one you just save.

    Let me know if it does not work

    Regards,
    Daniel
  3. 0
    Martin Dawson ·

    Izam In your mpp file, make

    Izam

    In your mpp file, make sure the top line is NOT blank.

  4. 0
    Pieter Bezuidenhout ·

    If you cant import mpp to P6

    If you cant import mpp to P6 convert it to XML that usualy works for me if you can convert it to MPX even better.