Filters/Layouts when import p3 into p6

G TMember for 15 years 10 months
Created
1
21
0

Dear All,

Would u pls help me with my question...

Suppose u build a schedule in p3.... u orginised by some groups, u applied some filters.... and eventually u come up with your layouts.
Now when u open this layout in p3 it is opend exactly is same organised way as u prepared.
But when u import it into p6 ... all your filters/or group bands that u organised are gone ?.... isnt it?
You should again apply the filters/or apply "organise" according your initial seetings correct ?
In P6 it gives u just a bunch of all activities without any filters/or layouts which u set in p3 ? correct ?

I opened neatly organised p3 in p6 ang got just bunch of all my actvivities in an unorganised way...

 

Rgds

GT
 

1 reply

Oldest first
  1. 0
    Ferdinand U. ·

    yes to all your

    yes to all your questions.

    just do the layout/filter again in p6