PRA Cost Roll Up
In the Open Standard
Simon MartinMember for 18 years 8 months
- Created
- 0
- 2
0
Hi,
In the Risk Outputs tab of PRA, the P50 cost does not seem to roll up properly. For example the sum of the P50 costs of activities do not always equal the P50 cost of their WBS element, and the sum of the P50 costs of WBS elements does not always equal the P50 cost of their parent WBS element.
Has anyone else had this issue?
Any assistance would be greatly appreciated.
Kind regards,
Simon
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?