Reasons to use multiple links between the tasks
In the Open Standard
Evgeny Z.Member for 18 years 9 months
- Created
- 1
- 5
0
Dear all,
possibility to use multiple links between the same 2 tasks is quoted as one of the Spider’s advantage. However the only application of this I could think of is to have SS and FF links from Activity 1 to Activity 2. In case Activity 2 is a hammock type, then it will mirror the duration of Activity 1.
Are there any other applications of these feature?
Regards.
Evgeny