Rates, Norms & Durations / Tunnelling & Mining

Headings & Hand Tunneling

Headings & Hand Tunneling entries
ActivityEntry (verbatim)Source
Vertical ShaftsVertical Shafts Vent shaft 10 m dia, build 1 m/day, excavate at 80 m3/day Vent shaft connecting tunnels 6m dia, build 0.75 m/day, excavate at 21 m3/day4 rate statements found; left for an editorVertical Shafts

1–1 of 1

These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.