Rates, Norms & Durations / Roads & Infrastructure

Road Surfaces

Barber Greene 8798 machine laying 100 mm in two coats (m2/hr)... Tarmacadam = 160.0 Asphalt = 145.0 Manual laying 100 mm in two coats (m2/hr)... Tarmacadam = 7.7 Asphalt = 5.0 Average laying of Asphalt wearing Course=40 Ton/hr so one crew can do 400 ton of asphalt /day
Road Surfaces entries
ActivityEntry (verbatim)Source
Concrete Road surfacingTask / DescriptionSlow Ave Fast Units Concrete Road surfacing, Kerbs or Side Haunches- 0.4 - m3/hr Concrete Road surfacing, 150mm thick- 12.5 - m2/hr Concrete Road surfacing, 200mm thick- 7.7 - m2/hr Concrete Road surfacing, 300mm thick- 6.7 - m2/hrConcrete Road surfacing

1–1 of 1

These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.