Barber Greene 8798 machine laying 100 mm in two coats (m2/hr)...

  • Tarmacadam = 160.0
  • Asphalt = 145.0

Manual laying 100 mm in two coats (m2/hr)...

  • Tarmacadam = 7.7
  • Asphalt = 5.0
  • Average laying of Asphalt wearing Course=40 Ton/hr so one crew can do 400 ton of asphalt /day