Steel

Steel entries
ActivityEntry (verbatim)Source
ExternallyOne coat primer, 2 undercoats, 1 gloss 1.70 m2/hr As above to steel stanchions and beams 0.90 m2/hr As above to balustrades, railings etc 1.00 m2/hr As above to gutter and downpipes etc 2.50 m/hr4 rate statements found; left for an editorExternally
InternallyOne coat primer, 1 undercoat, 1 gloss 2.40 m2/hr As above to steel stanchions and beams 1.30 m2/hr As above to balustrades, railings etc 1.40 m2/hr3 rate statements found; left for an editorInternally

1–2 of 2

These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.