Rates, Norms & Durations
Externally
In the Open Standard
Started by Oliver Melling ·
- Last updated
- Updated
- Views
- 9 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →
One coat primer, 2 undercoats, 1 gloss 1.70 m2/hr
As above to steel stanchions and beams 0.90 m2/hr
As above to balustrades, railings etc 1.00 m2/hr
As above to gutter and downpipes etc 2.50 m/hr