Adjust start date when schedule has logic applied to it

Austin RobinsonMember for 8 years
Created
3
4
0

Hello everyone, I am a construction student using asta to build a schedule for a project I am working on. Now, I have built the entire schedule start to finish, but unfortunetly I have forgotten to add my preconstruction tasks, which, are required for my project. I established the start date (Notice to Proceed) for 10/12/2018 and proceeded with my schedule logic. I would like to have the preconstruction tasks starting on 8/27/2018 and move in logical order on the schedule. However, every time I reschedule, it moves the start date of my precon tasks up to 10/12/2018 regardless of constraints removed and changing the start date in bar chart format tab. Please let me know if anyone can help. Thank you - Austin

3 replies

Oldest first
  1. 0
    Andrew Willard ·

    Hi File-Properties-Advanced

    Hi

     

    File-Properties-Advanced properties -change the imposed start date.

     

    Also make sure the date of the project report date is the new date you want

     

    Andrew

  2. 0
    Mike Testro ·

    Hi Austin - Welcome to

    Hi Austin - Welcome to Planning Planet

    You can also set week 1 as the works start date by right click the date zone and set the date for weeks 1.

    Earlir dates will show as minus numbers.

    Best regards

    Mike T.

  3. 0
    Austin Robinson ·

    Thank you Mike and Andrew.

    Thank you Mike and Andrew. Those helped me.

     

    Regards,

    Austin