Column Heading Shading / Font Colour Change

Taner AyselMember for 7 years 6 months
Created
1
1
0

Hi All, 

 I would like to change column heading row shading / background colour to light grey when I am printing out programme in ASTA powerproject, 

 Does anyone know how to do it?

Your help would be really appreciated, 

 Regards

Taner

1 reply

Oldest first
  1. 0
    Barry Casey ·

    Format Tab > Hierarchy

    Format Tab > Hierarchy Appearance > Choose colour