Compensation Events & NEC Option C
In the Open Standard
Stuart AtkinsonMember for 22 years 9 months
- Created
- 5
- 2
0
I am currently having an ongoing discussion with my colleagues concerning the effective management of the programme within the NEC.
In brief my view is this-
An EW is raised.A EW meeting is arranged. From this meeting it can be ascertained by the client & contractor whether measures can be implemented to lessen or negate negative effects on the project.If it cannot be avoided (or has already past)any time implication should be presented on the programme showing any delay to completion. If the client agrees to the extension of time it will be then incorporated into the next programme update; and becomes the ’latest accepted programme’
Question - After demonstrating a potential delay by way of an ’early warning programme’ showing the client any effect on programme, would you leave this EW duration within the programme if the client did not accept the time element of the CE.
In brief my view is this-
An EW is raised.A EW meeting is arranged. From this meeting it can be ascertained by the client & contractor whether measures can be implemented to lessen or negate negative effects on the project.If it cannot be avoided (or has already past)any time implication should be presented on the programme showing any delay to completion. If the client agrees to the extension of time it will be then incorporated into the next programme update; and becomes the ’latest accepted programme’
Question - After demonstrating a potential delay by way of an ’early warning programme’ showing the client any effect on programme, would you leave this EW duration within the programme if the client did not accept the time element of the CE.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?