Delayed Sectional Completion & following events
In the Open Standard
Andrew OwensonMember for 18 years 4 months
- Created
- 11
- 5
0
I am on a PPC2000 contract. I have a sectional completion which we handed over late, and is directly linked to another section of works with another sectional completion at the end. We handed over two weeks late and the duration of the next section of works is 12 weeks. Do I have to reduce the duration to 10 weeks or does the sectional completion get reset. We are not claiming an extention of time as it is our fault and there are no LAD’s involved.
Regards
Andrew
Regards
Andrew
11 replies