Outstanding vs Snag lists
In the Open Standard
Jihad DanielMember for 21 years 5 months
- Created
- 13
- 1
0
Dear Colleagues,
Under FIDIC regulations, a building is substantially completed when it passed all required tests. Therefore, a taking over certificate will be issued from the Engineer with the approval of the Employer. The Contractor shall be committed to a certain date to finalize the outstanding items. From the date of issuance of the taking over certificate, the Contractor will be working in the defect period.
But there is a difference in the terms of "outstanding items" and "snagged" or "punched items" as an outstanding item means that after realizing the E/M testing, an item or system is still not functioning well and its test failed. Snag item is a small defect or missing piece that does not affect the whole or separate system.
As an example, if a mechanical system passed the test but a small piece is missing or is defected. Does this mean that the building is still not substantially completed?
Regards,
J. Daniel
Under FIDIC regulations, a building is substantially completed when it passed all required tests. Therefore, a taking over certificate will be issued from the Engineer with the approval of the Employer. The Contractor shall be committed to a certain date to finalize the outstanding items. From the date of issuance of the taking over certificate, the Contractor will be working in the defect period.
But there is a difference in the terms of "outstanding items" and "snagged" or "punched items" as an outstanding item means that after realizing the E/M testing, an item or system is still not functioning well and its test failed. Snag item is a small defect or missing piece that does not affect the whole or separate system.
As an example, if a mechanical system passed the test but a small piece is missing or is defected. Does this mean that the building is still not substantially completed?
Regards,
J. Daniel
13 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?