Skip to content

Feed Documents/Drawing? or Technical Specifications?

David MosesMember for 21 years 11 months
Created
8
3
0
Hi There;

Assume that you are undertaking an EPC Project. And you have been given feed documents/drawings and technical specifications for HVAC for example by th client.

Can you claim for the equipments or any other materials which have not been mentioned or listed in the feed documents/drawings?

While the technical specifications describe the client requirements.

I mean is that true or false to use just feed documents/drawings for claiming? Not taking into account of the clients technical specifications.

Regards

8 replies

Oldest first
  1. 0
    Andrew Flowerdew ·
    Moses,

    No easy answer to that, but the starting position would be no you can’t.

    But from there you would have to ascertain what you took responsibility for when you took on the client information. Was it held out to be a complete design, just a rough idea of what was required, etc, etc.....


    Then define (legally speaking) what your scope of works is and what the contract says you can or can’t claim for. eg

    Please Mr Contractor design, procure and install a complete HVAC system for us. We have this preliminary design that show’s you the sort of thing we were thinking about but it’s up to you how you do it. Then no you can’t.

    or:

    Please Mr Contractor design, procure and install a complete HVAC system for us. We have this design that we want you to use and develop abit further but it’s substantially all there. Then maybe you can if the contract allows it.




  2. 0
    Ashraf Alawady ·
    My dear,
    You have to put in your mind the following issues:-
    1-All the contract documents are compelementary.
    2- Contract documents means
    contract agreement
    Tender condition of contract
    letter of acceptance
    condition of contract(general & particular)
    contract drawings
    contract specification(general & particular)
    contract BOQ
    official correspondences

    If you have received any instruction or any addetional datas (drawings) to do any works specified in any part of the above said documments ,then you can not use it to built
    a claim.

    If that instruction or addi.drawings wwere not specified in any part of the above mentioned contract document,then you have to notify the client and reserve your right for claiming any EOT and additional costs.

    Furthermore you have to make complete study and analysis using TIA to get the actual time impact and do cost analysis to get the cost immplecations - if any.



  3. 0
    David Moses ·
    Hi There,

    Since this is an EPC Project and a Lump Sum contract.We are responsible for Engineering based on the feed documents/drawings and clients Technical Specifications.

    Of course the clients inputs are not a complete design, just a rough idea of what is required. But till the finalisation of the Material Take Offs no party could estimate the exact cost for HVAC System.

    At this point for example, there are some more equipments required for the HVAC System based on our Engineering. Which complies with the clients Technical Specifications.

    Now, the client says your design is complying with our Technical Specifications but we can not pay for those equipments for the HVAC System which were not shown on the feed documents/drawings.

    Is this just our problem?

    Regards
  4. 0
    Ashraf Alawady ·
    *You are responsible for Engineering based on the feed documents/drawings and clients Technical Specifications.
    *Clients inputs are not a complete design.
    *SO, the client has to provide you wit just a rough idea of what is required and based on your professionality as specialest in this feild, you have to do the works including the detail design.

    In the light of the above ,you have to include all the expectd cost , as specialest in this feild, during your pricing for the total required scope of works as a lump sum contract.
    It seems that it is your own problem.
  5. 0
    John Whitney ·
    It also can depend on how the "feed documents" are presented to the contractor in the request for quotation.

    If it is a full-blown EPC, with a performance specification, then the contractor is responsible for everything (except design criteria) for bringing the works to successful completion, fit-for-purpose. BoQs and specification descriptions mean nothing in terms of giving grounds for claim.

    If it is a prescriptive specification, where the client tells you to incorporate certain items as requirement, there may be some scope for claim. However, if the contract expressly says that you must provide everything normally provided, whether stated in the contract or not, then you cannot claim.

    From my past 12yrs experience of EPC, I would say that, as a general rule, once you are into these kind of contracting arrangements, you have to provide everything unless there are clear provisions entitling you to claim written into the t&c.
  6. 0
    Andrew Flowerdew ·
    John seems to have summed it up quite well
  7. 0
    Ashraf Alawady ·
    Hi,David

    is it clear now or you still need more clarifications.

    REGARDS
  8. 0
    David Moses ·
    Hi There,

    I am so glad to see that all friends are trying to share as much as they can.

    I really appreciated for your valuable comments.

    Thanks

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?